BESIX in the news: From Creek to Canal

It’s been several decades in the making but finally the long-held ambition of extending the historic Dubai Creek back to the Arabian Sea has become a reality. The achievement marked the realisation of a dream of Sheikh Rashid bin Saeed Al Maktoum – one of the principal architects of the United Arab Emirates (UAE) 45 years ago and the late father of Sheikh Mohammed bin Rashid Al Maktoum, current Prime Minister of the UAE and Ruler of Dubai.

The first phase of the canal was completed more than a decade ago at a cost of AED 1bn and extended 9 km from Ras Al Khor through Business Bay to Sheikh Zayed Road (SZR). Like other big projects at the time, completing the final 6km stretch of the canal was put on the back burner while Dubai staged a recovery from the global financial crisis of 2008/9. But two years ago the project finally got the green light and in November the waterway was inaugurated in a spectacular ceremony overseen by Sheikh Mohammed.

Belgian contractor BESIX – through its local venture Belhasa Six Construct – was entrusted with the bulk of the works related to the new portion of the canal, which has turned a large part of central Dubai into an island. Jean-Pol Bouharmont, deputy general manager of Six Construct for the UAE, Oman, Qatar and Bahrain, was heavily involved in the process, especially during the final month to ensure it was delivered on time and to the specifications of the client – The Roads and Transport Authority (RTA).

The contractor was awarded two main packages of work. The first involved diverting all the underground utilities and carrying out canal excavation wherever possible while it waited for another contractor to build the bridges over the main canal crossings – SZR, Al Wasl Road and Jumeirah Beach Road. The second package involved treating the water in Business Bay – which had become hyper saline over a 10-year period – before releasing it safely back into the sea.

“The original creek extension was stopped with a series of utilities not diverted,” Bouharmont says. “In fact there was not just one lagoon in Business Bay but a series of them separated by bunts where the existing services were still in place. Due to a combination of evaporation, the tide and the dewatering of all the new buildings in the area (the dewatering was discharged into the lagoons) the water became highly saline over time. The biggest lagoon was more or less white as it was really hyper saline.”

Carrying out the water treatment package was quite challenging in terms of how to dilute the water to an acceptable mix before opening the canal, especially on the creek side. Six Construct pumped the hyper saline water all the way from the lagoon up to a mixing basin near a newly created peninsula at Jumeirah where it was blended with seawater to reduce the salinity before being discharged into the sea. The whole process took two months with another month to pump normal seawater back into the lagoon using a pair of 800mm pipes laid on the canal bed.

“This second package of work was awarded quite late in January 2016, where we had nine months to divert the services in Business Bay area, removing the bunts, pumping and mixing the seawater and then pumping seawater back into the lagoon,” says Bouharmont. “Then step by step the bridges were completed between April, for the first one, and July for the last one over SZR and we were able to excavate below the bridges and finally connect the canal to the sea.”

The final stage of excavation could only take place once the bridges were installed on top of the huge pillars holding them in place. The distance from the bridge to the bass of the canal is around 12 metres and each pillar goes a further four metres below ground level. Around 50,000 m3 of earth was excavated from beneath each bridge but at this point removing the earth had become quite straightforward. Because the rest of the canal was already excavated, construction traffic could travel along the canal bed to the artificial peninsula built using the excavated earth.

“There was quite a lot of traffic management during the two and a half years but that last part was not so difficult,” Bouharmont explains. “More difficult was installing the block work for the quay walls below those bridges. We got those areas quite late in the contract period and we had to be ready to expedite the work. We even coordinated with the client and the other contractor, especially on SZR bridge, to work on part of the quay walls while they were doing the foundation of the bridge. We didn’t wait for the bridge to be completed before building the wall.”

The quay walls were made using precast concrete blocks weighing 40 to 50 tonnes each. Every night during the construction period 30 to 50 blocks at a time were made in a special facility in Warsan, depending on the progress of installation. There is a ten metre wide promenade either side of the canal after which it’s safe to excavate to build alongside the canal.

“You would have some shoring to do but you can excavate without any problem although there will be some dewatering during construction,” he says. “Basically you are building a huge brick wall and then back filling behind the quay walls with some rock. Technically it was not so challenging building quay walls. The challenges were more involving traffic management and trying to minimise disturbance to the environment because it’s an area where you have a lot of villas. You have an extremely tight schedule but at the same time you have to try not to disturb too much during the night. But the challenge was more to do with traffic sequencing because of the bridges and diverting existing utilities.”

The latter involved recreating new networks for all the underground services – sewer lines, electricity, water pipes, telecoms, etc – that had previously passed through the site of the canal. The relocation of these services was a laborious process that took two years before excavation could begin. Tunneling was used where possible to minimise the impact on traffic and excavations.

Six Construct has plenty of experience doing some of what it was tasked with on this project while other elements were new. “It’s a unique project for sure. But it’s a mix of things we have done in different environments. I’ve been here for 20 years and I’ve always had at least two ongoing projects building quay walls with the same technique. So that’s nothing special. It’s more that it involved building in a heavily congested environment. But dealing with the hyper saline water is unique and it was necessary to investigate what would be the best solution. We had part of the expertise in house but for the pumping and mixing we used a specialist contractor.”

Another major challenge only came about very late in the process. Due to design issues, Six Construct was given the green light to proceed with a very significant portion of the work – construction of three pedestrian bridges and the canal promenades – in the last six months, leading to a logistical headache to complete the job on time.

It was here that Bouharmont became deeply involved. “Part of those bridges were executed while the canal was already flooded so we had to build temporary platforms over the canal to be able to build the bridges. There was a lot of sequencing into those bridges which are also technically quite challenging. When you see them now they are quite iconic. We used specialist sub-contractors to fabricate them but we had to help erect them.”

With this job under its belt Belhasa Six Construct says it is ready to take on the next challenge for the RTA, which has been a regular client for the past 20 years. Among other projects, the contractor has delivered Business Bay Bridge, Garhoud Bridge and is building the bridge to Deira Islands. It also completed work on the Dubai Tram two years ago.

Olivier Crasson, executive vice president, confirms Belhasa Six Construct is tendering for infrastructure work in the run up to Expo 2020. “The first packages for infra work are on the market and some have been awarded so we assume that the quantity of work related to Expo 2020 will increase, probably in 2017. But at the moment there is still not too much on the market.”

Belhasa Six Construct is also experienced in another fast growing sector of the Dubai construction sector, having recently completed work on Legoland, part of Dubai Parks and Resorts. In fact it also worked on Ferrari World in Abu Dhabi and is carrying out an expansion of the theme park. The company says it is in discussion for more work in the theme park arena.

The Canal in Numbers:

– 3.2 km long

– 80m to 120m wide

– 4m deep

– 3 road bridges and 3 pedestrian bridges

– 250,000 m2 of area reclaimed on the sea

– 800m of new beach along reclaimed area

– 2.8 million m3 of excavation

– 9,400 concrete blocks

– 27,000 m3 of concrete for diaphragm wall

Recent news items
48 Dutch companies present at ADIPEC 2017
Mon 20 November 2017 - 11:19:00
Four Belgians among list of European innovators under 35
Mon 20 November 2017 - 10:55:00
6 November: Behind the scenes: VeBes O&M Company
Thu 09 November 2017 - 10:17:00
Etihad Airways Promotion
Wed 08 November 2017 - 10:50:00
Become a member of the BeNeLux Business Council now and receive 4 months for free!
Sun 17 September 2017 - 9:08:00
Eid Mubarak
Wed 30 August 2017 - 7:08:00
Luxembourg is the most productive country in the world in 2017!
Thu 17 August 2017 - 11:26:00
Abu Dhabi named second best city to live and work in
Mon 17 July 2017 - 2:57:00
Expo2020 Dubai: Invitation to Food & Beverage BusinessConnect
Wed 05 July 2017 - 11:13:00
Eid Mubarak
Sat 24 June 2017 - 9:28:00
Eid Mubarak
Sat 24 June 2017 - 9:28:00
The Dutch Have Solutions to Rising Seas. The World Is Watching.
Thu 22 June 2017 - 11:02:00
Etihad Airways: Boeing 787 network in Europe expanded
Sun 04 June 2017 - 10:02:00
Ramadan Kareem
Fri 26 May 2017 - 9:00:00
The Embassy of the Grand Duchy of Luxembourg is hiring!
Sun 14 May 2017 - 10:43:00
The Dutch have first place, Belgium third and Luxembourg 19th place of the most globalised countries
Tue 02 May 2017 - 1:12:00
UAE tops list of ‘safest country in the world’
Mon 24 April 2017 - 11:44:00
Wage gap decreasing most rapidly of all in Belgium
Sun 16 April 2017 - 12:13:00
The Embassy of the Kingdom of Belgium in Abu Dhabi is hiring!
Wed 05 April 2017 - 8:55:00
Netherlands to join Expo 2020
Sun 26 March 2017 - 10:34:00
UAE prepares to celebrate International Women’s Day
Thu 09 March 2017 - 9:46:00
Happy Woman’s Day to all our members and friends!
Wed 08 March 2017 - 3:19:00
Embassy of the Kingdom of the Netherlands: Job vacancies
Sun 05 March 2017 - 9:25:00
Etihad Airways Promotion
Mon 20 February 2017 - 10:02:00
Global Awareness Day
Sun 12 February 2017 - 8:05:00
Holland+You: explored business opportunities to support Dutch companies.
Mon 16 January 2017 - 9:49:00
The BBC has a very sportive Board of Directors !
Sun 15 January 2017 - 9:27:00
BESIX in the news: From Creek to Canal
Thu 12 January 2017 - 11:13:00
Best Wishes for 2017!
Tue 06 December 2016 - 9:42:00
Best wishes on the occasion of the UAE’s 45th National Day
Tue 06 December 2016 - 9:23:00
Belgian astronaut inspires Emirati youth on space exploration
Thu 24 November 2016 - 5:58:00
Ahmed Aboutaleb, Mayor of Rotterdam and prominent Dutch politician visiting Abu Dhabi
Wed 05 October 2016 - 8:24:00
UAE leads Arab World in innovation
Wed 07 September 2016 - 10:32:00
Eid Mubarak
Mon 04 July 2016 - 11:20:00
Eid Mubarak
Mon 04 July 2016 - 11:20:00
The force behind women empowerment in the UAE
Tue 14 June 2016 - 11:08:00
Ramadan Kareem
Sun 05 June 2016 - 6:23:00
Ramadan Kareem
Sun 05 June 2016 - 6:23:00
The UAE is an important trading partner
Thu 19 May 2016 - 10:50:00
Board positions open at the BeNeLux Business Council – do you want to join ?
Thu 28 April 2016 - 10:34:00
Koningsdag
Wed 27 April 2016 - 9:05:00
Attacks in Brussel
Thu 24 March 2016 - 10:49:00
The Embassy of the Kingdom of the Netherlands in Abu Dhabi is hiring
Mon 07 March 2016 - 12:40:00
The Embassy of the Grand Duchy in Abu Dhabi is looking to hire an Accounting/Consular Assistant.
Mon 07 March 2016 - 12:40:00
UAE to implement VAT at the rate of 5% on 1 January 2018
Thu 03 March 2016 - 11:09:00
Interview Paul Boelens with the Energy Board Room on 17th of December 2015 which was published 16/02
Sun 21 February 2016 - 2:02:00
Expo 2020 Report *(updated ToR and deadline)
Thu 04 February 2016 - 8:59:00
Etihad Tickets
Tue 12 January 2016 - 9:38:00
Best wishes on the occasion of the UAE’s 44th National Day
Mon 30 November 2015 - 11:37:00
European Film Screenings
Wed 14 October 2015 - 11:43:00
Report Back to Business event
Thu 01 October 2015 - 8:56:00
Renew your membership now and fly for free!
Wed 23 September 2015 - 12:09:00
Eid Mubarak
Tue 22 September 2015 - 12:32:00
Some things better left unseen: Presenting artwork at the Louvre Abu Dhabi
Thu 17 September 2015 - 11:38:00
Departure Ambassador Jennes de Mol
Tue 15 September 2015 - 4:55:00
Report dedicated to the Netherlands by Khaleej Times
Thu 03 September 2015 - 12:28:00
New location Embassy of the Kingdom of the Netherlands
Thu 03 September 2015 - 11:57:00
Everything about doing business in the UAE - Abu Dhabi
Thu 20 August 2015 - 4:10:00
Consular Government liaison officer/consular assistant/translator (ENG/ARAB) - Nederlandse Ambassade
Thu 04 June 2015 - 5:21:00
The first speed-networking event was a success!
Sun 24 May 2015 - 9:54:00
Louvre Abu Dhabi - Meyvaert Glass Engineering
Sun 10 May 2015 - 8:33:00
New Board BeNeLux Business Council
Thu 07 May 2015 - 7:14:00
Belgian firm wins deal to supply Louvre Abu Dhabi display cases
Sun 12 April 2015 - 9:58:00
A Short Term Assistant (m/f) for the Dubai office - AWEX
Tue 27 January 2015 - 5:27:00